Commercial roofs ยท Pine Hills
Commercial roofing in Pine Hills, FL
Pine Hills has 24,609 housing units, and with a median build year of 1980, many multi-unit buildings and association properties here are likely carrying older low-slope roofs. Orange County Division of Building Safety permits that work, since Pine Hills is unincorporated. Roof size and condition decide your path.
Updated October 2026

Permits and code
Who permits a commercial roof in Pine Hills
Pine Hills is a census-designated place, not a city, so you do not file with Orlando. Orange County Division of Building Safety handles it, and applications and inspection requests go through the county's Fast Track portal. Before you sign a contract, check that office to learn what its submittal steps are right now.
Only Broward and Miami-Dade counties fall inside the High-Velocity Hurricane Zone. Orange County work follows the regular Florida Building Code, not the HVHZ product-approval and uniform permit forms. Check the code edition too: the Ninth Edition takes effect December 31, 2026, and applications filed on or after that date must meet it.
A permit does not last forever. If work has not started within 6 months, or if it stops for 6 months, the permit becomes invalid. Active progress is shown by an approved inspection that falls within 180 days.
Building stock
Older buildings and the 25 percent rule
In Pine Hills, 49.0 percent of housing units were built before 1980, against 26.1 percent countywide. Only 1.5 percent date from 2010 or later. That suggests many apartment and association buildings here have roofs that have been patched more than once.
Patching has a limit. No more than 25 percent of a roof section may be repaired, replaced or recovered in any 12-month period unless the whole section is redone. Only when that roof itself was built, repaired or replaced under the 2007 Florida Building Code or a later edition does the exception apply.
Recover over the old membrane is barred where the roof is water soaked, or already has two or more roof coverings. In those cases the work goes to the deck. Ask for a moisture survey before anyone prices a recover.
Bid checklist
Comparing bids on a flat roof
Orlando's rainfall normals show about 51 inches a year, with 45 percent falling in June through August. Drainage matters on a low-slope roof. New low-slope roofs need a minimum design slope of one-fourth unit in 12, and the code defines positive drainage as water gone within 48 hours of rain.
- Membrane type and its ASTM standard: TPO under D6878, modified bitumen under D6162 and related standards.
- Secondary overflow drains or scuppers where the parapet can trap water.
- The edge metal was tested using the ANSI/SPRI ES-1 methods.
- Who pulls the permit, and whether a Notice of Commencement is recorded before the first inspection.
Existing rooftop equipment does not have to be brought up to code unless it is replaced or moved during reroofing. Ask each bidder how they handle the units on your roof.
Questions
Commercial roofing in Pine Hills: questions
Does Pine Hills fall in the High-Velocity Hurricane Zone?
No. Just two counties, Broward and Miami-Dade, make up the High-Velocity Hurricane Zone. Pine Hills is in Orange County, so your roof follows the standard Florida Building Code. That means no HVHZ uniform permit application and no Miami-Dade Notice of Acceptance requirement. Products still need statewide Florida product approval, which you can look up by FL number on the Florida Building Commission search.
Source: FBC-Building 2023 Chapter 2 definitions, read Oct 5, 2026
Where do I get a commercial roof permit in Pine Hills?
Apply through Orange County Division of Building Safety, which issues permits for Pine Hills because it is unincorporated. The county takes new applications and inspection requests online through its Fast Track portal. Confirm current requirements with the building office. If you hire a contractor, the permit card also warns the owner about recording a Notice of Commencement before the first inspection.
Source: Orange County Division of Building Safety, read Oct 5, 2026
Can a contractor just recover my old flat roof?
Sometimes, but not always. A recover is barred where the existing roof is water soaked or has two or more roof coverings, and full tear-off to the deck is required. With 49.0 percent of Pine Hills homes built before 1980, many older roofs here may already have layers. A moisture survey before bidding shows which route applies.
Source: 2023 Florida Building Code, Building, 8th ed., Chapter 15 (UpCodes viewer, unofficial transcription), read Oct 5, 2026
What roof slope does a new low-slope roof need?
A minimum design slope of one-fourth unit in 12, which is 2 percent, is required for new built-up, modified bitumen, single-ply, spray foam and liquid-applied roofs. Drainage must clear water within 48 hours of rain. Secondary overflow drains or scuppers are required wherever parapets could hold back water. Orlando-area rainfall of about 51 inches a year makes this worth checking in every bid.
Source: FBC-B 2023 Ch. 15, read Oct 5, 2026
Sources for this page(23)
- 1.Permit office: Orange County Division of Building Safety. Orange County Division of Building Safety. Read Oct 10, 2026.
- 2.Orange County Government, Division of Building Safety. Read Oct 5, 2026.
- 3.U.S. Census Bureau, American Community Survey 2020-2024 5-year estimates (acs2024_5yr), via Census Reporter API, table B25034. Read Oct 5, 2026.
- 4.U.S. Census Bureau, American Community Survey 2020-2024 5-year estimates (acs2024_5yr), via Census Reporter API, tables B25034/B25035. Read Oct 5, 2026.
- 5.U.S. Census Bureau, American Community Survey 2020-2024 5-year estimates (acs2024_5yr), via Census Reporter API, table B25035. Read Oct 5, 2026.
- 6.NOAA NCEI, U.S. Climate Normals 1991-2020 (annual/seasonal), access-data API. Read Oct 5, 2026.
- 7.Housing units (ACS 5-year): 24,609. U.S. Census Bureau, American Community Survey 2020-2024 5-year estimates (acs2024_5yr), via Census Reporter API. Read Oct 5, 2026.
- 8.FBC-Building 2023 Chapter 2 definitions. Read Oct 5, 2026.
- 9.Miami-Dade County RER notice. Read Oct 5, 2026.
- 10.2023 Florida Building Code, Building, 8th ed., Chapter 1 (UpCodes viewer, unofficial transcription). Read Oct 5, 2026.
- 11.2023 Florida Building Code, Building, 8th ed., Chapter 15 (UpCodes viewer, unofficial transcription). Read Oct 5, 2026.
- 12.FBC-B 2023 Ch. 15. Read Oct 5, 2026.
- 13.2023 Florida Building Code, Plumbing, 8th ed., Chapter 11 (UpCodes viewer, unofficial transcription). Read Oct 5, 2026.
- 14.Florida Statutes, section 553.842 (2026). Read Oct 5, 2026.
- 15.Florida Building Commission. Read Oct 5, 2026.
- 16.Orange County Division of Building Safety, ocfl.net. Read Oct 5, 2026.
- 17.Florida Statutes, section 713.135 (2026), Florida Legislature. Read Oct 5, 2026.
- 18.Citizens Property Insurance Corporation, inspections FAQ (updated 2026-03-17), Citizens Property Insurance. Read Oct 4, 2026.
- 19.NWS Melbourne, Post Tropical Cyclone Report: Hurricane Irma (2017), National Weather Service. Read Oct 5, 2026.
- 20.NWS Melbourne, Post Tropical Cyclone Report: Hurricane Matthew (2016), National Weather Service. Read Oct 5, 2026.
- 21.NOAA Atlas 14 Volume 9 version 2, partial-duration 24-hour depth estimates at the Pine Hills 2020 Census internal point (28.5818, -81.4695), NOAA Hydrometeorological Design Studies Center. Read Oct 5, 2026.
- 22.FRSA, "New 2023 FBC Eighth Edition is Now in Effect", 2024-02-13, floridaroof.com. Read Oct 5, 2026.
- 23.Fla. Stat. 489.105(3)(e), Florida Legislature. Read Oct 5, 2026.